Centennial Picnic Shelter

Project Info
  • Construction Date: March 2020
  • Location: Brock Rd, Pickering
  • Values: 352,797.30
  • Category: Featured Projects, Parks & Community Centers
  • Client : City of Pickering
Project Details

Scope of this Project Includes Excavation Asphalt Concrete Pad- Shade Structure Concrete Footing for Shade Structure Drainage Pipe Trees   Challenges: While Digging the Holes for footings the earth profile is not the same as Geo-Technical (No Stiff Soil) report so didn’t support the design which was given during tender submission. Solution: Proposed Helical Piers […]

More Project Details

Scope of this Project Includes

  1. Excavation
  2. Asphalt
  3. Concrete Pad- Shade Structure
  4. Concrete Footing for Shade Structure
  5. Drainage Pipe
  6. Trees

 

Challenges: While Digging the Holes for footings the earth profile is not the same as Geo-Technical (No Stiff Soil) report so didn’t support the design which was given during tender submission.

Solution: Proposed Helical Piers for the footings Obtained design from Techno Metal Post and a Change order has been approved.